The elected president of Venezuela Edmundo González Urrutia had to flee to Spain and is currently in exile in that country after the regime issued an arrest warrant against him for subversion. González Urrutia obtained 67% of the votes in the election day of July 28, against 30% for Nicolás Maduro with 83.5% of the votes verified with published tally sheets, winning in all states (source: resultadosconvzla.com). We reject the arrest warrant, and the fraud intended by the National Electoral Council – CNE of Venezuela, proclaiming Nicolás Maduro as president-elect for a new presidential term and its ratification by the Supreme Court of Justice-TSJ, both without showing the voting minutes or any other support.  EnergiesNet ” Latin America & Caribbean web portal with news and information on Energy, Oil, Gas, Renewables, Engineering, Technology, and Environment.– Contact : Elio Ohep, editor at  EnergiesNet@gmail.com +584142763041-   The elected president of Venezuela Edmundo González Urrutia had to flee to Spain and is currently in exile in that country after the regime issued an arrest warrant against him for subversion. González Urrutia obtained 67% of the votes in the election day of July 28, against 30% for Nicolás Maduro with 83.5% of the votes verified with published tally sheets, winning in all states (source: resultadosconvzla.com). We reject the arrest warrant, and the fraud intended by the National Electoral Council – CNE of Venezuela, proclaiming Nicolás Maduro as president-elect for a new presidential term and its ratification by the Supreme Court of Justice-TSJ, both without showing the voting minutes or any other support.
10/28 Closing Prices / revised 10/29/2024 08:18 GMT | 10/28 OPEC Basket  $71.59 –$2.22 cents | 10/28 Mexico Basket (MME)  $62.55 –$4.36 cents |  09/30 Venezuela Basket (Merey) $54.91   -$7.24 cents  10/28 NYMEX Light Sweet Crude $67.38 -$4.40 cents | 10/28 ICE Brent Sept $71.42 -$4.63 cents | 10/28 Gasoline RBOB NYC Harbor  $2.9257 -0.113 cents | 10/28 Heating oil NY Harbor  $2.1398 -0.1093 cents | 10/28 NYMEX Natural Gas $2.863 +0.229 cents | 10/18 Active U.S. Rig Count (Oil & Gas) = 585 0 | 10/29 USD/MXN Mexican Peso 20.0092 (data live) 10/29 EUR/USD  1.0814 (data live) | 10/29 US/Bs. (Bolivar)  $41.73610000 (data BCV) | Source: WTRG/MSN/Bloomberg/MarketWatch

Guyana’s EPA orders Environmental Impact Assessment for Exxon’s 5th project

Stakeholders have 28 days to submit queries

Kaieteur News

GEORGETOWN
EnergiesNet.com 05 06 2022

Following its submission of an application to the Environmental Protection Agency (EPA) for permission to undertake a fifth deepwater project at the Uaru oil field in the Stabroek Block, ExxonMobil Guyana has been ordered to conduct an Environmental Impact Assessment (EIA).
In a missive seen by Kaieteur News, the EPA said the proposed project will be implemented in multiple stages which include the following activities: well drillings and completions, mobilization and installation of subsea equipment, umbilicals, risers and flowlines (SURF), installation of a floating production, storage and offloading (FPSO) facility, production operations, and decommissioning.

The agency said the proposed project will be undertaken in the marine offshore environment and would require land-based activities for support activities at marine shore bases. As a result of the intended developmental activities, it said possible effects to the environment may include impacts on marine water quality, air quality, marine fauna, socio-economic resources, among others.
In keeping with the Environmental Protection Act and the foregoing impacts, the EPA has determined that this project may significantly affect the environment and will require an Environmental Impact Assessment before any decision can be made as to its approval or rejection.
The EPA said citizens now have approximately 27 days to make written submissions to the agency, setting out those questions and matters which they require to be answered or considered in the EIA. In its project summary Exxon’s subsidiary, Esso Exploration and Production Guyana Limited (EPPGL) which operates the Stabroek concession said the Uaru Project will be located in the eastern portion of the block, approximately 200 km from Georgetown and amid previous Stabroek Projects.
Current plans include drilling via drillships to produce oil from approximately 40-76 wells. Production is expected to begin between the fourth quarter of 2026 and the second quarter of 2027 with an expected field life of at least 20 years. EEPGL said the production facilities to be installed include subsea equipment attached to the seafloor as well as processing equipment on the ocean’s surface known as a Floating, Production, Storage, and Offloading (FPSO) vessel. EEPGL said this subsea equipment is installed at approximately 1,450 – 1,950 m of water depth while noting that the main components of the subsea kit include the following: production tree, production manifold, flowlines, risers, and umbilicals. The subsea umbilicals, risers, and flowlines are commonly referred to as SURF.

Additionally, EEPGL’s document explained that the oil, gas, and water flow from the well into the production tree. The fluids are then gathered into the manifold which then connects to the flow lines before the risers take the fluids up to the FPSO for processing. Kaieteur News understands that the umbilical lines support production by providing real time control of the subsea installation from the surface by delivering fluids to facilitate the flow of hydrocarbons. As for the FPSO, it is an industrial floating complex that continuously separates oil from produced water and associated gas for onboard storage, and later transfer to third party tankers. The anticipated production rate for the FPSO ranges between approximately 220,000 barrels and 275,000 barrels of oil per day. The vessel will be capable of storing approximately two million barrels of oil.

Furthermore, third party oil tankers will be scheduled to offload the oil from the FPSO, making the oil available for export to the international market. The FPSO will also process, dehydrate, compress, and reinject associated gas produced from the reservoir. As the Uaru and Mako reservoir pressures deplete over time, this gas reinjection will help maintain reservoir pressure and allow for optimum production of hydrocarbons to continue over time. In addition, some of the gas will be used as fuel on the FPSO.

kaiteurnewsonline.com 05 05 2022

Share this news

Support EnergiesNet.com

By Elio Ohep · Launched in 1999 under Petroleumworld.com

Information & News on Latin America’s Energy, Oil, Gas, Renewables, Climate, Technology, Politics and Social issues

Contact : editor@petroleuworld.com


CopyRight©1999-2021, EnergiesNet.com™  / Elio Ohep – All rights reserved
 

This site is a public free site and it contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.We are making such material available in our efforts to advance understanding of business, environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have chosen to view the included information for research, information, and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use’, you must obtain permission fromPetroleumworld or the copyright owner of the material.