01/10 Closing Prices / revised 01/10/2025 21:59 GMT  01/09 OPEC Basket  $76.13 –$0.80 cents | 01/10 Mexico Basket (MME)  $71.46 +$2.65 cents   11/30 Venezuela Basketc (Merey)  $59.58   +$1.28 cents  01/10 NYMEX Light Sweet Crude  $76.56   +$2.65 cents | 01/10 ICE Brent  $79.76 +$2.84 cents |  01/10 Gasoline RBOB NYC Harbor  $2.07 +2.3% 01/10 Heating oil NY Harbor  $2.50 +5.2%| 01/10 NYMEX Natural Gas $3.99   +7.8% | 01/10 Baker Hughes Rig Count (Oil & Gas) 584 -6 | 01/10 USD/MXN Mexican Peso    $20.7161 (data live) | 01/10 EUR/USD Dollar $1.0244 (data live) | 01/14 US/Bs. (Bolivar)  $53.87910000 (data BCV) | Source: WTRG/MSN/Bloomberg/MarketWatch/Reuters

Mexico’s Maya Train Project to Cost Up to $20 Billion, 70% Over Budget -Bloomberg

Andres Manuel Lopez Obrador points to a map with the route of the Mayan Train that is under construction during the daily briefing at Palacio Nacional on June 28, 2022 in Mexico City. (Hector Vivas/Getty).

Andrea Navarro, Bloomberg News

MEXICO CITY
EnergiuesNet.com 07 27 2022

Mexico President Andres Manuel Lopez Obrador’s flagship Maya Train project will cost up to $20 billion, his second mega infrastructure project to be running wildly over-budget amid setbacks and soaring inflation.

Lopez Obrador announced the new $15 billion to $20 billion price tag at a press conference Tuesday, which is as much as 70% higher than the $11.9 billion budget the government had previously announced.

The train’s budget has increased in part because prices for shipping and raw materials have risen steeply. The original route has also undergone several changes and court suspensions amid concerns over the environmental impact from the project, while Lopez Obrador has insisted it be inaugurated by the end of 2023, adding pressure for builders to finish the train at all costs.  

The president’s other key project, the Dos Bocas oil refinery, has also seen its cost spiral out of control to reach as much as $18 billion, more than double its original price tag.

On Monday, Lopez Obrador said Grupo Mexico SAB will no longer be in charge of building the south part of the train’s fifth section, apparently ending a contract with the company worth 15.4 billion pesos ($752 million).

bloomberg.com 07 26 2022

Share this news

Leave a Comment


 EnergiesNet.com

About Us

 

By Elio Ohep · Launched in 1999 under Petroleumworld.com

Information & News on Latin America’s Energy, Oil, Gas,
Renewables, Climate, Technology, Politics and Social issues

Contact : editor@petroleuworld.com


CopyRight©1999-2024, Petroleumworld.com
, EnergiesNet.com™  /
Elio Ohep – All rights reserved
 

This site is a public free site and it contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.We are making such material available in our efforts to advance understanding of business, environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have chosen to view the included information for research, information, and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use’, you must obtain permission fromPetroleumworld or the copyright owner of the materia

 

Energy - Environment

No posts found!

Point of View

EIA Total Energy Review
This Week in Petroleum